Important Features / Notes
Our engineering team was deputed along with metallurgical personnel with spectrometer to site during shutdown. We have identified all combination of material specifications. Also we measured complete coils at site to prepare necessary fabrication drawing, obtained statutory approval and supplied the coils. The Alloy steel tubes conforming to ASME standards with 5% notch tested were procured from IBR approved well known tube bends. Tube of sizes OD 54mm and various thickness were used. The entire assembly was subject to a Stress relieving Heat Treatment operation after completion of manufacture.
Project Completion
2010